Biosolids capacity expansion inspection services
Summary
An amendment with Hillis Carnes for specialized inspection services on the biosolids capacity expansion was scheduled — part of the county's wastewater infrastructure investment.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Sep 15, 2026.
Impact analysis
The amendment adds inspection costs to the biosolids expansion project.
County wastewater system users who rely on expanded biosolids capacity.
Ratepayers could face costs from the bond and the above-estimate contract price.
Mentions & discussions (3)
Levy Court Business - Sep 15, 2026
An amendment with Hillis Carnes for specialized inspection services on the biosolids capacity expansion was scheduled — part of the county's wastewater infrastructure investment.
Levy Court Business - Apr 14, 2026
A net $57,517 change order improves stormwater drainage at the biosolids site and matches the control building exterior to the adjacent maintenance garage.
Levy Court Business - Feb 10, 2026
The final phase of the biosolids project came in at $24.5 million versus a $14 million estimate, thanks to inflation and only one bidder. Finishing it ends a $2 million-a-year Denali contract and satisfies a DNREC requirement, but the county will take on an obligation bond of roughly $8 million.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Kent County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.