Milford Corporate Center Phase 1

Description

Council approved a 49-day no-cost extension of the construction deadline to August 28, 2026, and separately (4-3) reduced retainage from 6% to 3% on the roughly $18 million contract.

Impact summary

The project is 89% done and expected to wrap by late August; the city will accept it around September with a performance bond securing the one-year guarantee.

Applicant

Name
George & Lynch

At a glance

Hearings
1
Public comments
0
Total mentions
1

Last vote · City Council

Approved7–0, unanimous

Last discussed Jun 22, 2026.