Milford Corporate Center Phase 1
Description
Council approved a 49-day no-cost extension of the construction deadline to August 28, 2026, and separately (4-3) reduced retainage from 6% to 3% on the roughly $18 million contract.
Impact summary
The project is 89% done and expected to wrap by late August; the city will accept it around September with a performance bond securing the one-year guarantee.
Applicant
- Name
- George & Lynch
At a glance
- Hearings
- 1
- Public comments
- 0
- Total mentions
- 1
Last vote · City Council
Last discussed Jun 22, 2026.
Meeting timeline (1)
Related issues (1)
We'll email you when it's on an upcoming agenda, when it's voted on and when its status changes, at most once a day.
The weekly brief for Milford
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.