Riverwalk Wall Repair and Fishing Platform Location
Summary
A storm-damaged section of the Riverwalk has been fenced off for over a year. Council picked the living shoreline option with a fishing platform, costing up to $504,700, partly by redirecting City Hall Plaza funds. Repairs should restore a key downtown attraction before summer.
At a glance
- Total mentions
- 2
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Oct 12, 2026.
Impact analysis
Up to $504,700 from reserves, with about $293,000 expected to be returned to general fund reserves.
Riverwalk users, anglers, and downtown businesses.
Mentions & discussions (2)
City Council - Oct 12, 2026
The snow-damaged riverwalk concrete wall and the restroom project are grinding through design approvals. Councilmember James asked that the public get a say on where the fishing platform goes, likely through the Parks and Rec Advisory Board.
City Council - Mar 23, 2026
A storm-damaged section of the Riverwalk has been fenced off for over a year. Council picked the living shoreline option with a fishing platform, costing up to $504,700, partly by redirecting City Hall Plaza funds. Repairs should restore a key downtown attraction before summer.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Milford
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.